How the estimate is built
Each report's low, median and high fee comes from the 2026 benchmark schedule, adjusted for asset class (Phase I risk tier) and building size (PCA, ALTA, BER sampling). Rush delivery adds 30% at the low end, 35% at the median and 40% at the high end. Portfolios get 5% off from 3 sites, 10% from 6 and 15% from 11.
The critical path is the longest report's turnaround, plus reliance letters where selected, plus five business days for the lender's review. The latest order date counts that back from your closing date in business days.
What the program selection changes
- SBA 7(a) / 504: an RSRA for general commercial property, a Phase I for Appendix 6 uses (the high-risk and manufacturing classes), and reliance to the lender.
- Fannie Mae / Freddie Mac: Phase I with BER screening, PCA, reliance.
- CMBS: Phase I, PCA, ALTA survey, zoning report, reliance.
- HUD MAP: Phase I, 20-year PCNA (priced 25% above a standard PCA), BER screening, ALTA, reliance.